Технологические решения для нефтепереработки · Практический пример

Northshore CC827494: Calcium removal from high-calcium crude at the desalter

A refinery in North China combined Cestoil’s Northshore CC827494 with a monitored desalter injection program. Seven analysed days averaged 83% calcium removal, while the refinery reported lower calcium on FCC equilibrium catalyst and reduced fresh-catalyst consumption.

Обсудить аналогичное применение Запросить образец
Refinery process equipment
Изображение варианта применения; не фотография объекта заказчика.

Условия деятельности и цель

The refinery’s 1.8 million tonnes/year crude unit processed a crude slate made up entirely of high-calcium offshore crudes. Calcium varied from about 30 ppm to more than 200 ppm with the blend. Conventional desalting did not adequately remove the oil-soluble calcium naphthenates.

The plant reported high desalter current, increased power consumption and trips. Calcium carried into atmospheric and vacuum residue and VGO was associated with FCC catalyst poisoning, particle agglomeration, riser plugging and interrupted fluidisation. Equilibrium-catalyst calcium had reached 17,660 µg/g, and fresh-catalyst make-up had increased to 3.9 kg per tonne of FCC feed.

The trial target was calcium removal above 70% across the desalter train, without modifying desalter metallurgy or mechanical equipment.

Продукция и техническое обслуживание

Northshore CC827494 is a water-soluble calcium-removal agent applied through desalter wash water. It reacts with oil-soluble calcium naphthenates to form a water-soluble complex that leaves with the brine. The reported program maintained high removal at neutral to weakly alkaline effluent pH.

Cestoil designed injection ahead of each stage’s wash-water static mixer on the three-stage desalter train, supported by a pretreatment aid at the crude charge pump. The team monitored inlet and outlet calcium and iron, desalter currents, effluent pH and chemical oxygen demand (COD).

Dosing began on 18 September 2008, immediately after the crude unit restarted from turnaround. Oversized metering pumps initially made precise dose control difficult. On 29 September, Cestoil installed dedicated metering pumps: 110 L/h for stages 1–2 and 170 L/h for stage 3. With all three stages dosed, the total dose was adjusted from an initial 343 ppm toward 120–215 ppm while performance and effluent quality were reviewed.

Application and trial conditions

Reported crude-unit and desalter conditions
ПараметрReported condition
Crude throughput during trial3,500–4,000 tonnes/day
Desalter trainThree stages; injection before the wash-water static mixers
Desalter temperature110–130 °C
Desalter pressure0.7–0.8 MPa, as reported
Wash-water rate5–8%
Calcium in crude on analysed days31–76 ppm at the inlet; 3.6–14 ppm after desalting

Metering-pump figures are equipment ratings, not the chemical injection rates used throughout the trial. Dose was adjusted to crude calcium and operating response.

Reported calcium-removal results

Seven analysed days in 2008, as reported in the case-study figure
Sampling dateTotal CC827494 doseCalcium removal
19 September343 ppm71.2%
20 September180 ppm90.4%
22 September180 ppm88.2%
24 September240 ppm71.6%
26 September282 ppm80.0%
29 September215 ppm89.7%
2 October120 ppm88.4%

All seven analysed days exceeded the 70% target. Mean removal was approximately 83%. At 76 ppm inlet calcium, 180 ppm of CC827494 achieved 90.4% removal, giving a reported product-dose-to-calcium ratio of approximately 2.4.

The observed range was 71.2–90.4%; the 80–90% headline in the supplied PDF does not describe every analysed day. These data reflect changing feed and treatment conditions, rather than a controlled dose-response test.

FCC and desalter observations

Customer-reported FCC comparison: late July versus 8 October 2008
IndicatorBeforeAfter
Calcium on equilibrium catalyst17,660 µg/g3,444 µg/g
Catalyst micro-activity68.671.4
Fresh-catalyst consumption3.9 kg/t FCC feed1.2 kg/t FCC feed
FCC light-product yield73.7%80.1%
FCC total liquid yield78.2%83.8%
FCC throughput940 tonnes/day1,292 tonnes/day

Fresh-catalyst consumption fell by 2.7 kg/t, approximately 69% from the reported endpoints. Light-product and total-liquid yields increased by 6.4 and 5.6 percentage points, respectively. The refinery attributed the gain chiefly to calcium removal, while noting that FCC equipment upgrades also contributed; the comparison does not isolate the chemical program’s share of the yield increase.

Third-stage desalter currents reportedly fell from 64–87 A to 30–50 A within a day of dosing. The plant reported lower power consumption, no trips and clear effluent water during the monitored period.

As dosing was optimised, effluent pH moved from 4.5 to 7.1–7.5, while COD decreased from 13,697 to 3,199 mg/L, approximately 77%. Calcium removal remained at 88–90% in the reported optimisation comparison. No corrosion was found in the reported evaluation.

Reported economic value

Historical annualised economics and throughput bases
ItemRefinery’s basisAnnual amount
FCC fresh-catalyst saving2.7 kg/t reduction; RMB 51.86 per tonne of FCC feed; 350,000 tonnes/year FCC basisApproximately RMB 18.2 million/year
Decalcifier program costRMB 5 per tonne of crude; 1.8 million tonnes/year crude basisRMB 9.0 million/year
Derived net benefit before yield benefitsCatalyst saving less decalcifier cost, using the reported annual totalsAbout RMB 9 million/year

These are annualised figures based on the refinery’s 2008 report, not a full year of measured net savings or a current price quotation. Catalyst savings are expressed per tonne of FCC feed, while chemical cost is per tonne of crude. Feed calcium, throughput, chemical prices, catalyst cost and unit changes affect the economics at another site.

Применение полученных результатов

Measure calcium in incoming crude receipts so treatment can follow crude-slate changes. The refinery identified delayed knowledge of cargo calcium content as a principal operating difficulty.

Use metering pumps sized for the intended dose range. Track calcium removal together with desalter currents, effluent pH and COD, and plan for calcium-bearing brine at the wastewater plant. Review equilibrium-catalyst metals, fresh-catalyst addition and FCC yields over several catalyst turnovers, accounting for feed changes and equipment upgrades.

Обсудить аналогичное применение

Share your crude calcium and iron range, crude-slate variability, desalter stages and operating conditions, wash-water rates and injection points, equilibrium-catalyst metals, fresh-catalyst consumption and FCC yields. Cestoil’s technical team can help define an injection program and a monitored trial.

Свяжитесь с нашей технической командой

Source: Customer trial report, refining division, crude distillation unit at a refinery in North China, September–October 2008, as summarised in Cestoil case study CS-CDU-CC827494-2026A, v1.0. All operating and cost figures are reported by the customer; percentage changes and derived net benefit are rounded from the reported figures.

Performance reflects the specific field-trial conditions. Actual results may vary with feed quality and operating conditions. Users are responsible for determining product suitability for their operations.

Ознакомьтесь со всеми примерами проектов